Question: When recognizing revenue over time on a long-term contract, the percent complete is often estimated by comparing the cost incurred to date with the total

When recognizing revenue over time on a long-term contract, the percent complete is often estimated by comparing the cost incurred to date with the total estimated cost to complete. True or False True False 4