Question: When resolving resource decisions in multi-project environments, if a project manager assigns resources based upon minimizing idle time, this is called: Greatest Resource Utilization Greatest
When resolving resource decisions in multi-project environments, if a project manager assigns resources based upon minimizing idle time, this is called:
Greatest Resource Utilization
Greatest Resource Demand
Minimum Late Finish Time
Mathematical Programming