Question: When resources are adequate yet demamd varies over the span of a project, it might be a good idea to even out resources by delaying
When resources are adequate yet demamd varies over the span of a project, it might be a good idea to even out resources by delaying noncritical activites to lower peak demand.This practice is called
Question 1 options:
a)
allocation
b)
shifting
c)
smoothing
d)
manipulating