Question: When resources are adequate yet demamd varies over the span of a project, it might be a good idea to even out resources by delaying

When resources are adequate yet demamd varies over the span of a project, it might be a good idea to even out resources by delaying noncritical activites to lower peak demand.This practice is called

Question 1 options:

a)

allocation

b)

shifting

c)

smoothing

d)

manipulating