Question: When scheduling activities in a resource - constrained project, typically the activity scheduled first has the _ _ _ _ _ _ _ _ _

When scheduling activities in a resource-constrained project, typically the activity scheduled first has the __________ amount of slack.
Group of answer choices
greatest
least
most
modest
maximum