Question: When several activities need the same limited resource at the same time, the activities with Question 3 0 options: a . the least slack have
When several activities need the same limited resource at the same time, the activities with
Question options:
a the least slack have first priority.
b the longest duration have first priority.
c the near term have first priority.
d use the most resources have first priority.