Question: When statement best describes the difference between individual risks and overall project risk? Question 4 9 options: a ) Overall risk is the sum of

When statement best describes the difference between individual risks and overall project risk?
Question 49 options:
a)
Overall risk is the sum of the high severity individual risks on a project.
b)
Overall project risks is the amount of risks that the project is exposed to. Individual risks determines how to respond to individual events.
c)
Individual risks must be eliminated before overall project risks can be adressed.
d)
Individual risks affect specific tasks on a project, while overall risks relates to the risk of undertaking the project as a whole.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!