Question: When the final project plan is completed, what does the project manager first do ? Question 2 1 options: Circulate the final project plan to
When the final project plan is completed, what does the project manager first do
Question options:
Circulate the final project plan to the necessary stakeholders.
Place the final project plan in a file and proceed to the next phase.
Seek out scope changes in case of missing tasks.
Begin quality control of the tasks.