Question: When the project manager receives a performance report showing that the project is two weeks behind the schedule. He immediately took corrective actions to bring
When the project manager receives a performance report showing that the project is two weeks behind the schedule. He immediately took corrective actions to bring the project to the planned schedule. These activities took place during:
| A. | Project Planning | |
| B. | Project Execution | |
| C. | Project Implementation | |
| D. | Project Monitoring & Controlling |