Question: When the work in an activity is interrupted to work on another activity and is then resumed at a later point in time, it is

When the work in an activity is interrupted to work on another activity and is then resumed at a later point in time, it is called
Multiple Choice
prioritizing
preempting
overriding
splitting
All of these alternatives are correct