Question: When there is a 3 - day lag between the end of activity A and the start of activity B , then? Group of answer

When there is a 3-day lag between the end of activity A and the start of activity B, then? Group of answer choicesActivity B has to wait exactly 3 days after the completion of activity A before it can startActivity B has to wait at least 3 days after the completion of activity A before it can startActivity B has to wait at most 3 days after the completion of activity A before it can startActivity B cannot take more than 3 days in duration