Question: When three activities are scheduled in parallel, the critical path activity will be found on: Question 8 options: The shortest duration activity The longest duration

When three activities are scheduled in parallel, the critical path activity will be found on:
Question 8 options:
The shortest duration activity
The longest duration activity
The activity that is most important to the project
The activity that uses the most resources

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!