Question: When trying to optimize a project timeline, one limitation on use of fast-tracking is: Question 49Answer a. it can only be used on projects that
When trying to optimize a project timeline, one limitation on use of fast-tracking is: Question 49Answer a. it can only be used on projects that have no tasks in serial order b. if can only be used once within a project, as it will not produce benefits if used subsequent times c. only activities on the critical path will provide immediate timeline benefit for fast tracking since all the other activities have float d. none of the above