Question: When trying to recover lost time on a project schedule, a project manager considered cutting scope. Where is the first place to look for
"When trying to recover lost time on a project schedule, a project manager considered cutting scope. Where is the first place to look for opportunities to cut the schedule by eliminating scope?" O A. Tasks on the critical path. B. Resource histogram C. Project charter D. Gantt chart
Step by Step Solution
There are 3 Steps involved in it
The detailed answer for the above question is provided below When looki... View full answer