Question: When trying to track project benefits, a project manager realizes that some key performance indicators (KPis) are not yet defined. What should the project manager
When trying to track project benefits, a project manager realizes that some key performance indicators (KPis) are not yet defined. What should the project manager do? Ask the program manager to track and collect the missing data and work to buld the KPis E Work with the business analysts to track and collect the missing data and build the KPIs. Coordinate with the benefit owner to track and collect the missing data and build the KPis. Forward the issue to the benofit owner and ask them to collect the missing data and build the KPis