Question: When using objective information to determine the likelihood of different risks occurring on a project, project managers should not: Group of answer choices make sure
When using objective information to determine the likelihood of different risks occurring on a project, project managers should not: Group of answer choices make sure any conclusions are based on a sufficient number of prior situations consider previous experiences with projects similar to the current consider the opinions of as many people as possible none of the above
Step by Step Solution
There are 3 Steps involved in it