Question: When using PERT on a project with uncertain task times, the resulting distribution for the project duration is always asymmetric, with lower values taking more

When using PERT on a project with uncertain task
When using PERT on a project with uncertain task times, the resulting distribution for the project duration is always asymmetric, with lower values taking more weight always asymmetric, with higher values taking more weight O symmetric or asymmetric, depending on the distributions fitted to the individual tasks O always symmetric