Question: When using PERT to develop a project schedule, it is assumed that the expected durations of the activities follow what kind of probability distribution? A.

When using PERT to develop a project schedule, it is assumed that the expected durations of the activities follow what kind of probability distribution?

A.

Beta distribution

B.

Gamma distribution

C.

Negative binomial distribution

D.

F-distribution