Question: When using PERT to develop a project schedule, it is assumed that the expected durations of the activities follow what kind of probability distribution? A.
When using PERT to develop a project schedule, it is assumed that the expected durations of the activities follow what kind of probability distribution?
| A. | Beta distribution | |
| B. | Gamma distribution | |
| C. | Negative binomial distribution | |
| D. | F-distribution |