When using the below information, calculate the rated capacity if increasing 10% of the productivity.
- No. of machines : 10.
- No of shifts : 2.
- Workers per shift : 1 shift - 8 workers. 2 shift - 5 workers.
- Utilization = 80%.
- Efficiency = 90%.
- Working hours per week = 40 hours.