Question: When using the net present value (NPV) method in the project evaluation: a. One should accept all mutually exclusive projects with positive NPVs. b. One
When using the net present value (NPV) method in the project evaluation:
a.
One should accept all mutually exclusive projects with positive NPVs.
b.
One should accept all independent projects with positive NPVs.
c.
One should accept the independent project with the highest NPV.