Question: When we analyze a project and what will happen to the project's NPV if our most optimistic and pessimistic estimates come to pass, we are

When we analyze a project and what will happen to the project's NPV if our most optimistic and pessimistic estimates come to pass, we are engaging in the practice of
Multiple Cholce
Scenario analysis.
Contingency planning.
Simulation analysis.
Sensitivity analysis.
Triple-checking.