Question: When work package estimates are made by individuals most knowledgeable about the work being performed and these estimates are then rolled up to find
When work package estimates are made by individuals most knowledgeable about the work being performed and these estimates are then "rolled up to find estimated costs for major deliverables and the project itself, estimating is being used.
topdown
reference class
analogoug
pfoeffsional estimation
bottomup