Question: Where there is concurrent delay, the contractor is entitled to an extension of time but is not entitled to loss or expense incurred during the

Where there is concurrent delay, the contractor is entitled to an extension of time but is not entitled to loss or expense incurred during the extended period. This approach to dealing with concurrent delays is called:
Apportionment approach
Malmaison Approach
Dominant Cause Approach
Relevant Delay Approach