Question: Whether an IT project is seen as successful depends on what success criteria are considered. Which one of the following success criteria are largely outside

Whether an IT project is seen as successful depends on what success criteria are considered. Which one of the following success criteria are largely outside the Project Managers control?

a.

Completed project was within set timeframe

b.

Completed project realised projected benefits

c.

Completed project was under budget

d.

Completed project met all specified functional requirements

Which one of the following is not true about developing the project budget?

a.

It has to take into account costs that are not task related

b.

It does not need to consider human resources since the project team is made up of organisational employees

c.

It requires information about the resources required for each task

d.

It is a bottom-up exercise based on the tasks identified in the work breakdown structure

Collecting data to analyse project performance is a key activity for

a.

Quality management planning

b.

Quality assurance

c.

Quality control

d.

Continuous improvement

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!