Question: Which activities start one or more path and which activities end a path? Reference Activity Duration (weeks) Predecessors A Hire workers 8 None B Install

  1. Which activities "start" one or more path and which activities "end" a path?
Which activities "start" one or more path and
Reference Activity Duration (weeks) Predecessors A Hire workers 8 None B Install equipment 6 None C Order materials 3 None D Test equipment 4 B E Train workers 6 A, B F Pilot testing 5 C, D