Question: Which activity is crashed to get 2 days reduction at the lowest cost ( letter only! )? How many activities have to be crashed to
- Which activity is crashed to get 2 days reduction at the lowest cost (letter only!)?
- How many activities have to be crashed to achieve a five day reduction ?
- What is the (minimum) extra cost for achieving a five day reduction?

2. Three critical path activities are candidates for crashing on a project network. The need is to crash the project five days at the lowest cost plan. No other paths will become critical following a reduction or any combination of reductions of these activities. Assume crashing costs proportional to the duration