Question: Which approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items? a . analogy b .

Which approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items?
a.
analogy
b.
bottom-up
c.
top-down
d.
mind mapping