Question: Which approach to capacity management would require that the workforce be multi - skilled and easily adapt to being moved from line to line? Group
Which approach to capacity management would require that the workforce be multiskilled and easily adapt to being moved from line to line?
Group of answer choices
time flexibility from workforce
use of seasonal workforce
use of subcontracting
use of dual facilitiesdedicated and flexible
designing product flexibility into the production processes
Step by Step Solution