Question: Which cost estimating technique involves summing the costs of work packages? Rule of thumb Deliverable Parametric Bottoms - up Rough order of magnitude
Which cost estimating technique involves summing the costs of work packages?
Rule of thumb
Deliverable
Parametric
Bottomsup
Rough order of magnitude