Question: Which estimating technique is the best choice if you know the durations of similar activities from other projects? a . Analogous estimating. b . Parametric

Which estimating technique is the best choice if you know the durations of similar activities from other projects?
a.
Analogous estimating.
b.
Parametric estimating.
c.
Three-point estimating.
d.
Historical analysis estimating.