Question: Which has the highest possibility to be changed in a resource-constrained project? Select one: A. The completion date B. The budget C. Project quality D.
Which has the highest possibility to be changed in a resource-constrained project?
Select one:
A. The completion date
B. The budget
C. Project quality
D. Resource levels
E. Scope creep
Which of the following is correct statement?
Select one:
A. A risk response is established only for moderate risks while contingency plans are established for major risks.
B. A risk response is part of the actual implementation plan and action is taken before the risk can materialize, while a contingency plan goes into effect only after the risk has transpired.
C. A risk response is only effective when you are able to assess the likelihood of the risk and its impact on the project; all other risks are covered by contingency planning.
D. A risk response is created by the project team and the project manager while the project manager and the customer agree on the contingency plan.
E. A risk response is action that is the response to a risk once it has happened and the contingency plan is created by the customer if the risk response fails.