Question: which is correct assuming the project being considered has normal cash flows. the higher the cost of capital used to calculate NPV , the lower
which is correct assuming the project being considered has normal cash flows. the higher the cost of capital used to calculate NPV the lower the calculated NPV will be if a project's NPV is greater than zero, then its IRR must be less than the cost of capital. if a projects NPV is greater than zero, its IRR must be less than zero.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
