Question: Which is NOT correct about Decomposition in project scope management? Group of answer choices When it breaks down upper WBS levels, lower level components should

Which is NOT correct about Decomposition in project scope management?
Group of answer choices
When it breaks down upper WBS levels, lower level components should be displayed in chronological order.
It decomposes the upper WBS levels into lower-level detailed components.
It is not the only technique that can be used to create a WBS.
It is a technique used to create a WBS.