Question: Which is the best statement regarding work breakdown structure? OA. A packet is the smallest unit of work effort consuming both time and resources

Which is the best statement regarding work breakdown structure? OA. A packet is the smallest unit of work effort consuming both time and resources that the project manager can schedule and control. OB. WBS should not include a task representing planning of the project that is being planned. OC. A Level 1 activity is a more micro view (greater level of detail) than a Level 2 activity. OD. Each activity in the WBS must have an "owner" who is responsible for doing the work.
Step by Step Solution
3.39 Rating (149 Votes )
There are 3 Steps involved in it
WBS is defined as a Work Breakdown Structure It i... View full answer