Question: Which item below would be submitted by the contractor as part of a realistic work plan and Critical Path Method (CPM) schedule? a. A plan
Which item below would be submitted by the contractor as part of a realistic work plan and Critical Path Method (CPM) schedule?
a. A plan and schedule without the need for coordination with the owner and the designer
b. A schedule that includes activities related to sustainability
c. A work plan and CPM schedule that focuses on conforming to the contractor's workload rather than the contract requirements
d. A schedule that does not consider equipment start-up since is technically part of commissioning
Step by Step Solution
3.45 Rating (158 Votes )
There are 3 Steps involved in it
The detailed answer for the above question is provided below The best option for a realistic work pl... View full answer