Question: Which items are necessary in calculating the net present value of a project? I. Investment outlays II. Discount rate III. Incremental cash flow IV. Time

Which items are necessary in calculating the net present value of a project?

I. Investment outlays

II. Discount rate

III. Incremental cash flow

IV. Time period for the project

I, II and IV

I, II and III

II, III and IV

All of the above