Question: Which method is used to estimate project duration based on the assumption that task times are uncertain? Analogous Estimating Three - Point Estimating CPM (
Which method is used to estimate project duration based on the assumption that task times are uncertain?
Analogous Estimating
ThreePoint Estimating
CPM Critical Path Method
BottomUp Estimating
Monte Carlo Simulation