Which of the following descriptions about a critical path in anetwork diagram is INCORRECT? Critical path activities
Fantastic news! We've Found the answer you've been seeking!
Question:
Which of the following descriptions about a critical path in anetwork diagram is INCORRECT?
Critical path activities may have non-zero slack.
A critical path determines the minimum time required for projectcompletion.
There may be multiple critical paths.
Crashing non-critical path activities has no impact on theminimum time required for project completion.
Delaying an activity on a critical path delays the minimum timeneeded for project completion.