Question: Which of these represents a typical problem that can make it difficult to estimate activity durations accurately?Question 18 options:1)merging - multiple predecessors2)checklists and templates3)reducing sources
Which of these represents a typical problem that can make it difficult to estimate activity durations accurately?Question 18 options:1)merging - multiple predecessors2)checklists and templates3)reducing sources of uncertainty in the estimate4)carefully authorizing the start of non-critical activities