Activity A is worth $404, is 39% complete, and has actually cost $301. Activity B is worth $544, is 62% complete, and has actually cost $134 so far. Activity C is worth $564, is 66% complete, and has actually cost $257 so far. Estimated cost at completion for this project, assuming current variances are typical of future variances, is close to Select one: O a. 396.84 o b. 692.00 O c. 212.23 O d. 1206.70Step by Step Solution