Question: Which one of the following will decrease the net present valueof a project? Group of answer choices Increasing the project's initial cost at time zero.
Which one of the following will decrease the net present valueof a project?
Group of answer choices
Increasing the project's initial cost at time zero.
Increasing the amount of the final cash inflow
Decreasing the required discount rate
Moving each of the cash inflows forward to a sooner timeperiod
Step by Step Solution
3.48 Rating (151 Votes )
There are 3 Steps involved in it
Explanation The net present value is the present value of the project... View full answer