Question: Which option below is the correct sequence of a Risk Management process according to ISO 3 1 0 0 0 ? a . Establishing context,
Which option below is the correct sequence of a Risk Management process according to ISO
a Establishing context, communication and consultation, risk identification, risk analysis, risk evaluation, risk reduction, monitoring and reviewing
b Establishing context, risk identification, risk analysis, risk reduction, monitoring and reviewing, risk evaluation communication and consultation
c Establishing context, risk identification, risk analysis, monitoring and reviewing, risk evaluation, risk reduction
d Establishing context, communication and consultation, risk reduction, risk analysis, risk evaluation, risk identification, monitoring and reviewing