Question: Which output document from the risk management process contains information on potential risk owners? Risk Register Risk Categorization Risk Exposure Risk Report What is an
- Which output document from the risk management process contains information on potential risk owners?
Risk Register
Risk Categorization
Risk Exposure
Risk Report
- What is an input to the plan risk management process?
Project Charter
- Which quantitative data evaluation technique should a project manager use to determine alternative paths for managing risk in a project?
Sensitivity analysis
Decision tree analysis
Schedule network diagram
Influence diagram
- Which risk response strategy should a project manager use when the overall project risk is significantly positive and outside the agreed-upon risk thresholds for a project?
Mitigate
Transfer
Exploit
Avoid
- Which outcome is outside the scope of formal project management office?
Program
Portfolio
Plan
Product
- A project manager updates a project budget plan to include an additional 150.000 required by the supplier on top of the parts and labor negotiated.
Cost plus fixed fee
Cost plus incentive fee
Cost plus reimbursable fee
Cost plus award fee
- Which selection method is used in Procurement Management when a buyer asks seller to prepare technical and financial proposal?
Qualifications Only
Least Cost
Sole Source
Fixed budget
- What is a benefit of the emerging practice of trial engagements in Procurement Management?
Allowing buyers to choose which vendors product they will pay for
Putting sellers into a competitive relationship to reduce cost
Providing an opportunity to assess vendors while proceeding with project work
Improving the ability to employ agile development to complete scope