Question: Which phase in the project life cycle involves evaluating expected costs, benefits, and risks? a) conception b) feasibility analysis or study c) planning d) execution
Which phase in the project life cycle involves evaluating expected costs, benefits, and risks? a) conception b) feasibility analysis or study c) planning d) execution e) termination 4. Who is responsible for the success and failure of a project? a) the CEO b) the program manager c) the project manager d) the project sponsors e) the functional manager