Question: Which planning process converts the MPS into requirements for key resources in order to test the feasibility of a proposed MPS? Select one: a. Rough-cut

Which planning process converts the MPS into requirements for key resources in order to test the feasibility of a proposed MPS? Select one: a. Rough-cut capacity planning b. Trial-and-error c. Aggregate planning d. Trade-off analysis e. Master production scheduling