Question: Which planning process has the primary objective of balancing supply and demand over a medium - range time period, typically 3 to 1 8 months?
Which planning process has the primary objective of balancing supply and demand over a mediumrange time period, typically to months?
Master Production Scheduling
Capacity Requirements Planning
Final Assembly Schedule
Aggregate Production Planning