Question: Which PRINCE 2 process is described by the following statement: This is an ongoing process from start to finish. The initiation, stage boundaries, ad hoc
Which PRINCE process is described by the following statement:
This is an ongoing process from start to finish. The initiation, stage boundaries, ad hoc directionguidance and project closure are managed by the project board.
Task Answer
and.
Managing product delivery
b
Directing a project
C
Initiating a project
d
Controlling and stage