Question: Which project document is created early in the executing phase and is also an integral part of the closing phase and process group? Communication Management

Which project document is created early in the executing phase and is also an integral part of the closing phase and process group? Communication Management Plan Lessons Learned Register Risk Register Stakeholder Matrix A project has been terminated due to lack of executive support and necessary resources. Which of the below best describes this type of project termination? Termination-by-integration Project extinction Termination-by-addition Termination-by-starvation Which of the following is a common control mistake? Emphasizing short-run results at the expense of long-run objectives. Excessively controlling specific objectives and sacrificing other project objectives. Across-the-board cuts in resource allocations tend to penalize the frugal and efficient. All of the above