Question: Which Project Scope Management process creates the scope baseline. A . Plan Scope Management B . Control Scope C . Create WBS D . Validate

Which Project Scope Management process creates the scope baseline.
A. Plan Scope Management
B. Control Scope
C. Create WBS
D. Validate Scope