Question: Which project(s) should a firm choose when the projects are independent? When they are mutually exclusive? Suppose both are within the capital budget and k

Which project(s) should a firm choose when the projects are independent? When they are mutually exclusive? Suppose both are within the capital budget and k is 15 percent for both projects.

Project A: CF0 = $1750; CF1 = $850; CF2 = $3850; CF3 = $1350 Project B: CF0 = $1750; CF1 = $850; CF2 = $850; CF3 = $4250

Both projects; project A

Neither project; neither project

Both projects; project B

Project B; project B