Question: Which Resource is the bottleneck? What is it's Implied Utilization? Steps 2&4, 69% Step 3, 125% Step 5, 81% Step 3, 112% Given a bottleneck

Which Resource is the bottleneck? What is it's Implied Utilization?
| Steps 2&4, 69%
| ||
| Step 3, 125%
| ||
| Step 5, 81%
| ||
| Step 3, 112%
|
Given a bottleneck utilization of 112% (assume changes were made since question 1), determine the Actual Flow Rate for all 3 Products A, B, C. What is the sum total Flow Rate of the 3 Products?
Given a bottleneck utilization of 132% (assume more changes since question 2), determine the average daily profit for all three products if the profit per each product is:
A: $11.10
B: $ 7.20
C: $ 5.40
6. Consider a process consisting of five resources that are operated 8 hours per day. The process works on three different products, A, B, and C: Page 137 Number of Processing Time for Processing Time for B Processing Time for C Resource Workers A (minutes) (minutes) (minutes) 1 2 5 5 5 2 2 4 4 5 3 1 15 O 0 4 1 0 3 3 5 2 6 6 4 Demand for the three different products is as follows: product A, 40 units per day; product B, 50 units per day; and product C, 60 units per dayStep by Step Solution
There are 3 Steps involved in it